34th Avenue Reconstruction

The 34th Avenue reconstruction project will take place on 34th Avenue, between 34th Avenue Place and 50th Street. The project will be constructed in stages, in order to allow residents on 44th Street Court and 45th Street North to access their homes.

The project will include pavement replacement with 8” of concrete, sidewalk repairs, driveway repairs, some water main replacement including services, and other associated work.

This project is funded through local funds, including tax funds for electric and gas usage.

This project is Stage 4 of 5 of the total 34th Avenue Reconstruction, between 41st and 60th Streets. The final stage is 34th Avenue between 53rd and 56th Street Place, and is currently scheduled for construction in 2020. This project was chosen due to deteriorating pavement condition.

Timeline: Spring/Summer 2019

Contractor: Walter D. Laud, Inc.

Capital Improvement Project: #1309

Funds:

•    Tax on Electric Gas and Usage $660,000

•    Water $140,000

•    Sanitary Sewer $5,000

•    Stormwater $40,000

Contacts: Darrel Preston, Construction Manager

                (309) 524-2355

                dpreston@moline.il.us

               Scott Green, Resident Construction Inspector

               (309) 524-2356

              sgreen@moline.il.us