2019 Alley Reconstruction

The 2019 alley reconstruction project will take place on the alley facing East-West between 25th and 27th Streets, and Avenue of the Cities and 23rd Avenue Court.

The project will include pavement replacement with concrete, sidewalk repairs, driveway repairs, and other associated work.

This project is funded through local funds, including tax funds for electric and gas usage.

This project was chosen due to deteriorating pavement condition.

Timeline: Summer / Fall 2019

Contractor: T.B.D.

Capital Improvement Project: #1310

Funds:

• Tax on Electric Gas and Usage $115,000

• Stormwater $5,000

Contact: Darrel Preston, Construction Manager

                (309) 524-2355

                dpreston@moline.il.us