2019 Patching Program, Location #3

Moline’s 2019 Patching and Sidewalk Program will include 3 major patching locations.

Location #3 is Coaltown Road, 16th – 27th Street. As part of this project, deteriorating pavement will be removed and replaced as necessary.

This project is being funded with Local Options Sales Tax.

Timeline: Spring / Summer 2019

Contractor: Centennial Contractors of the Quad Cities, Inc.

Capital Improvement Project: #1322

Funds: Amounts listed below reflect the total cost for all patching and sidewalk locations.

•    Local Options Sales Tax $1,030,000

•    Water Funds $220,000

•    WPC Funds $125,000

Contacts: Darrel Preston, Construction Manager

                 (309) 524-2355

                 dpreston@moline.il.us

  Erin Bruner, Engineering Technician II

 (309) 524-2367

  ebruner@moline.il.us