This project will take place on 26th Avenue, between the 3800 block and 41st Street.
This project consists of replacing a culvert that runs north/south underneath 19th Avenue, just east of 34th Street. Project will also include significant grading to help relieve area of standing water.
Project Budget: $350,000
Timeline: Summer 2023
Contractor: Project scheduled to bid in March 2023
Contact: Darrel Preston, Construction Manager
(309) 524-2355